30 June 2006

-----------------------------------------------------------------------



[Federal Register: June 30, 2006 (Volume 71, Number 126)]

[Notices]               

[Page 37564-37567]

From the Federal Register Online via GPO Access [wais.access.gpo.gov]

[DOCID:fr30jn06-67]                         





[[Page 37564]]



-----------------------------------------------------------------------



DEPARTMENT OF ENERGY



Federal Energy Regulatory Commission



[Docket No. PF06-25-000; Docket No. PF06-26-000]



 

Jordan Cove Energy Project, L.P. and Pacific Connector Gas 

Pipeline, L.P.; Notice of Intent To Prepare an Environmental Impact 

Statement for the Proposed Jordan Cove LNG and Pacific Connector Gas 

Pipeline Projects, Request for Comments on Environmental Issues and 

Notice of a Joint Public Meeting



June 23, 2006.

    The staff of the Federal Energy Regulatory Commission (FERC or 

Commission) and the U.S. Department of Homeland Security, Coast Guard 

(Coast Guard) are in the process of evaluating the Jordon Cove 

Liquefied Natural Gas (LNG) Project planned by Jordan Cove Energy 

Project, L.P. (Jordan Cove), and the associated natural gas sendout 

pipeline planned by Pacific Connector Gas Pipeline, L.P. (PCGP). The 

project would consist of an onshore LNG import and storage terminal 

located on the bay side of the north spit of Coos Bay, Coos County, 

Oregon, and an approximately 223-mile-long, 36-inch-diameter natural 

gas pipeline extending from the Jordon Cove LNG terminal southeastward 

across Douglas, Jackson, and Klamath Counties, Oregon, to an 

interconnection with the existing Pacific Gas and Electric Company's 

(PG&E) pipeline system in Modoc County, California.

    As a part of this evaluation, the FERC staff will prepare an 

environmental impact statement (EIS) that will address the 

environmental impacts of the project and the Coast Guard will assess 

the maritime safety and security of the project. The FERC will produce 

a single comprehensive EIS to cover both the LNG terminal and sendout 

pipeline combined. As described below, the FERC and the Coast Guard 

will hold a joint public meeting in Coos Bay to allow the public to 

provide input to these assessments. The FERC will host additional 

public meetings along the pipeline route to provide input to the 

assessment of the pipeline component of the project.

    The Commission will use the EIS in its decision-making process to 

determine whether or not to authorize the project. This Notice of 

Intent (NOI) explains the scoping process we \1\ will use to gather 

information on the project from the public and interested agencies and 

summarizes the process that the Coast Guard will use. Your input will 

help identify the issues that need to be evaluated in the EIS and in 

the Coast Guard's maritime safety and security assessment. Please note 

that scoping comments are requested by July 24, 2006.

---------------------------------------------------------------------------



    \1\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 

of the FERC's Office of Energy Projects.

---------------------------------------------------------------------------



    Comments on the project may be submitted in written form or 

verbally. Further details on how to submit written comments are 

provided in the Public Participation section of this NOI. In lieu of 

sending written comments, we invite you to attend any of the following 

public scoping meetings scheduled as follows:



Monday, July 10, 2006, 6:30 p.m.: Umpqua Community College, Campus 

Center Dining Room/Timber Room, 1140 Umpqua College Rd., Roseburg, OR 

97470. 541-440-4600.

Tuesday, July 11, 2006, 6 p.m.: Southwestern Oregon Community College, 

Hales Performing Arts Center, 1988 Newmark Ave., Coos Bay, OR 97420. 

541-888-2525.

Wednesday, July 12, 2006, 7 p.m.: Red Lion Inn, Rogue River Ballroom, 

200 N. Riverside Ave., Medford, OR 97501. 541-779-5811.

Thursday, July 13, 2006, 6:30 p.m.: Oregon Institute of Technology, 

Auditorium, College Union, 3201 Campus Dr., Klamath Falls, OR 97601. 

41-885-1030.



    The second public scoping meeting listed above (Coos Bay) will be 

combined with the Coast Guard's public meeting regarding the maritime 

safety and security of the project. At the meeting, the Coast Guard 

will discuss: (1) The waterway suitability assessment that the 

applicant will conduct to determine whether or not the waterway can 

safely accommodate the LNG carrier traffic and operation of the planned 

LNG marine terminal; and (2) the facility security assessment that the 

applicant will conduct in accordance with the regulations of the 

Maritime Transportation Security Act to assist with the preparation of 

a Facility Security Plan. The Coast Guard will be issuing a separate 

meeting notice in the Federal Register for the maritime safety and 

security aspects of the project under Coast Guard District 13 docket 

number CGD13-06-028.

    The Coast Guard is responsible for matters related to navigation 

safety, vessel engineering and safety standards, and all matters 

pertaining to the safety of facilities or equipment located in or 

adjacent to navigable waters up to the last valve immediately before 

the receiving tanks. The Coast Guard also has authority for LNG 

facility security plan review, approval, and compliance verification as 

provided in Title 33 Code of Federal Regulations (CFR) Part 105, and 

recommendation for siting as it pertains to the management of vessel 

traffic in and around the LNG facility.

    Upon receipt of a letter of intent from an owner or operator 

intending to build a new LNG facility, the Coast Guard Captain of the 

Port conducts an analysis that results in a letter of recommendation 

issued to the owner or operator and to the state and local governments 

having jurisdiction, addressing the suitability of the waterway to 

accommodate LNG vessels. Specifically the letter of recommendation 

addresses the suitability of the waterway based on:

     The physical location and layout of the facility and its 

berthing and mooring arrangements.

     The LNG vessels' characteristics and the frequency of LNG 

shipments to the facility.

     Commercial, industrial, environmentally sensitive, and 

residential areas in and adjacent to the waterway used by the LNG 

vessels en route to the facility.

     Density and character of the marine traffic on the 

waterway.

     Bridges or other manmade obstructions in the waterway.

     Depth of water.

     Tidal range.

     Natural hazards, including rocks and sandbars.

     Underwater pipelines and cables.

     Distance of berthed LNG vessels from the channel, and the 

width of the channel.

    In addition, the Coast Guard will review and approve the facility's 

operations manual and emergency response plan (33 CFR 127.019), as well 

as the facility's security plan (33 CFR 105.410). The Coast Guard will 

also provide input to other Federal, state, and local government 

agencies reviewing the project.

    In order to complete a thorough analysis and fulfill the regulatory 

mandates cited above, the applicant will be conducting a Waterway 

Suitability Assessment (WSA), a formal risk assessment evaluating the 

various safety and security aspects associated with the Jordan Cove LNG 

proposed project. This risk assessment will be accomplished through a 

series of workshops focusing on the areas of waterways safety, port 

security, and consequence management, with involvement from a broad 

cross-section of government and port stakeholders with expertise in 

each of the respective areas. The workshops



[[Page 37565]]



will be by invitation only. However, comments received during the 

public comment period will be considered as input in the risk 

assessment process. The results of the WSA will be submitted to the 

Coast Guard to be used in determining whether the waterway is suitable 

for LNG traffic.

    This NOI is being sent to Federal, state, and local government 

agencies; elected officials; affected landowners; environmental and 

public interest groups; Indian tribes and regional Native American 

organizations; commentors and other interested parties; and local 

libraries and newspapers. We encourage government representatives to 

notify their constituents of this planned project and encourage them to 

comment on their areas of concern.



Summary of the Proposed Project



    The proposed project would consist of a 1.0 billion standard cubic 

feet per day (bscfd) capacity LNG import/storage terminal facility and 

a 223-mile-long, 36-inch-diameter sendout pipeline. A map depicting the 

general location of the Jordan Cove LNG import terminal and PCGP's 

proposed pipeline route is attached to this NOI as Appendix 1.\2\ 

Jordan Cove and PCGP indicated they intend to file their formal 

applications with the FERC on January 31, 2007.

---------------------------------------------------------------------------



    \2\ The appendices referenced in this notice are not being 

printed in the Federal Register. Copies are available on the 

Commission's Web site (excluding maps) at the ``e-Library'' link or 

from the Commission's Public Reference Room or call (202) 502-8371. 

For instructions on connecting to e-Library refer to the end of this 

notice. Copies of the appendices were sent to all those receiving 

this notice in the mail.

---------------------------------------------------------------------------



Jordan Cove LNG Import Terminal



    The proposed Jordon Cove LNG import terminal would include the 

following elements:

     Dredged 1,700-foot-diameter turning basin/ship maneuvering 

area located within Coos Bay;

     A single LNG ship unloading slip/berth, dredged from an 

upland adjacent to Coos Bay;

     LNG unloading system at the berth, consisting of three 16-

inch-diameter unloading arms and one 16-inch-diameter vapor return arm, 

with a unloading capacity rate of 12,000 cubic meters per hour 

(m3/hr);

     LNG transfer system from the berth to the storage tanks, 

consisting of one 2,600-foot-long, 36-inch-diameter cryogenic unloading 

line;

     LNG storage system, consisting of two full-containment LNG 

storage tanks, each with a capacity 160,000 m3 (or 1,006,000 

barrels). Each tank would be equipped with two can-type fully submerged 

LNG in-tank pumps with an individual capacity rate of 5,300 gallons per 

minute (gpm);

     Boil-off gas (BOG) recovery system, consisting of three 

cryogenic centrifugal BOG compressors, each with a rated capacity of 

2,300 cubic feet per minute (ft3/min), and two non-cryogenic 

reciprocating BOG pipeline compressors with an individual capacity 

rated at 2,500 ft3/min;

     LNG transfer system from the storage tanks to the 

vaporizers, consisting of six pot-mounted LNG booster pumps each sized 

for 2,200 gpm;

     LNG vaporizer system, consisting of six submerged 

combustion vaporizers each sized for 200 million standard cubic feet 

per day;

     A natural gas liquids (NGL) extraction facility, with the 

NGL to be sold to an entity other than Jordan Cove and transported from 

the terminal using existing railroad lines;

     A 30 megawatt, natural gas-fired, simple cycle combustion 

turbine power plant to provide a supplemental source of electric power 

for the LNG terminal;

     Waste heat recovery system;

     Emergency vent system, LNG spill containment system, fire 

water system, utility system, hazard detection system, and control 

system; and

     Buildings and support facilities.

    Jordan Cove proposes to initiate construction of the terminal in 

the winter of 2007-2008, and anticipates placing the project into 

service in the fourth quarter of 2010.



PCGP Sendout Pipeline



    The PCGP sendout pipeline would consist of the following elements:

     A 223-mile-long, 36-inch-diameter steel underground 

natural gas pipeline, extending from the proposed Jordon Cove LNG 

terminal southeast, crossing Coos, Douglas, Jackson, and Klamath 

Counties, Oregon, and into Modoc County, California, with capacity to 

deliver 1.0 bscfd at a maximum allowable operating pressure (MAOP) of 

1,440 pounds per square inch (psig);

     Butte Falls Compressor Station, at about Milepost (MP) 

127, Jackson County, Oregon, consisting of two new 10,310 horsepower 

compressor units;

     Interconnections with three existing natural gas pipeline 

systems, including Williams Northwest Pipeline's Grants Pass Lateral, 

PG&E's 400 and 401 pipelines, and potentially Tuscarora Gas 

Transmission's pipeline;

     Four receipt or delivery meter stations, including the 

Coos Bay Receipt Meter Station at MP 0.0 in Coos County, Oregon, the 

Clarks Branch Delivery Meter Station at about MP 68, Douglas County, 

Oregon, the Tulelake Delivery Station at MP 223, Modoc County, 

California, and the potential Tuscarora Delivery Meter Station also at 

MP 223;

     A gas control communication system, consisting of radio 

towers at each meter station, and the compressor station, and 

additional facilities at existing mountain top radio communication 

towers, and two new additional master radio sites at unspecified 

locations;

     Mainline block valves at 15 locations along the pipeline 

route; and

     Pig launchers and receivers located at each end of the 

pipeline (Coos Bay Meter Station and Tulelake Meter Station).

    PCGP proposes to begin construction of the sendout pipeline in the 

summer of 2009, and anticipates the completion of installation and 

restoration activities by the spring of 2011.



The EIS Process



    The NEPA requires the Commission to take into account the 

environmental impacts that could result from an action when it 

considers whether or not an LNG import terminal or an interstate 

natural gas pipeline should be approved. The FERC will use the EIS to 

consider the environmental impacts that could result if it issues 

project authorizations to Jordan Cove and PCGP under sections 3 and 7 

of the Natural Gas Act. The NEPA also requires us to discover and 

address concerns the public may have about proposals. This process is 

referred to as ``scoping.'' The main goal of the scoping process is to 

focus the analysis in the EIS on important environmental issues. With 

this NOI, the Commission staff is requesting public comments on the 

scope of the issues to be addressed in the EIS. All comments received 

will be considered during preparation of the EIS.

    In the EIS we will discuss impacts that could occur as a result of 

the construction, operation, maintenance, and abandonment of the 

proposed project under these general headings:

     Geology and Soils.

     Water Resources.

     Vegetation and Wildlife.

     Land Use, Recreation, and Visual Resources.

     Cultural Resources.

     Socioeconomics.

     Air Quality and Noise.

     Reliability and Safety.

     Cumulative Impacts.

    We will also evaluate possible alternatives to the proposed project 

or portions of the project, and make recommendations on how to lessen 

or avoid impacts on affected resources.



[[Page 37566]]



    Our independent analysis of the issues will be included in a draft 

EIS. The draft EIS will be mailed to Federal, state, and local 

government agencies; elected officials; affected landowners; 

environmental and public interest groups; Indian tribes and regional 

Native American organizations; commentors; other interested parties; 

local libraries and newspapers; and the FERC's official service list 

for this proceeding. A 90-day comment period will be allotted for 

review of the draft EIS. We will consider all comments on the draft EIS 

and revise the document, as necessary, before issuing a final EIS. We 

will consider all comments on the final EIS before we make our 

recommendations to the Commission. To ensure that your comments are 

considered, please follow the instructions in the Public Participation 

section of this NOI.

    Although no formal application has been filed, the FERC staff has 

already initiated its NEPA review under its pre-filing process. The 

purpose of the pre-filing process is to encourage early involvement of 

interested stakeholders and to identify and resolve issues before an 

application is filed with the FERC. In addition, the Coast Guard, which 

would be responsible for reviewing the maritime safety and security 

aspects of the planned project and regulating maritime safety and 

security if the project is approved, has initiated its review of the 

project as well.

    With this NOI, we are asking Federal, state, and local agencies 

with jurisdiction and/or special expertise with respect to 

environmental issues, to express their interest in becoming cooperating 

agencies for the preparation of the EIS. These agencies may choose to 

participate once they have evaluated the proposal relative to their 

responsibilities. The Coast Guard and the U.S. Army Corps of Engineers 

have already agreed to be cooperating agencies for this project. In 

letters dated May 9, 2006, we requested that the Oregon Department of 

Energy (ODE), U.S. Department of Agriculture Forest Service (USFS), 

U.S. Department of Commerce National Oceanic and Atmospheric 

Administration National Marine Fisheries Service (NMFS), U.S. 

Environmental Protection Agency, U.S. Department of the Interior Bureau 

of Land Management (BLM), and Fish and Wildlife Service also become 

cooperating agencies. The ODE and NMFS have declined our invitation to 

be cooperating agencies in the production of the EIS, but may 

reconsider at any time during the pre-filing review process.

    The EIS will examine the proposed action and alternatives that 

require administrative or other actions by other federal agencies. The 

USFS has identified the possible need to amend the existing Umpqua, 

Rouge River-Siskiyou, and Fremont-Winema National Forest Land and 

Resource Management Plans. The BLM has identified the possible need to 

amend the existing Resource Management Plans of the Coos Bay, Roseburg, 

and Medford Districts and the Klamath Falls Resource Area.



Currently Identified Environmental Issues



    We have already identified issues that we think deserve attention 

based on a preliminary review of the projects, and information provided 

by Jordan Cove and PCGP. This preliminary list of issues, which is 

presented below, may be revised based on your comments and our 

continuing analyses.

     Impact of LNG vessel traffic on other Coos Bay users, 

including commercial ships, fishing and recreational boaters.

     Potential impacts of dredging the turning basin and LNG 

ship dock on water quality and estuarine fishery resources.

     Potential impacts of the LNG terminal on residents in the 

Coos Bay area, including safety issues at the import and storage 

facility, noise, air quality, and visual resources.

     Potential impact of the LNG terminal on air traffic at the 

North Bend airport.

     Potential for geological hazards, including seismic 

activity, to have impacts on both the proposed LNG import terminal and 

sendout pipeline.

     Potential impacts of the pipeline on waterbodies and 

wetlands, including issues of erosion control.

     Potential impacts of the pipeline on vegetation, including 

the clearing of forest.

     Potential impacts of the pipeline on threatened and 

endangered species, and wildlife habitat.

     Potential impacts of the pipeline on cultural resources.



Public Participation



    You can make a difference by providing us with your specific 

comments or concerns about the planned project. By becoming a 

commentor, your concerns will be addressed in the EIS and considered by 

the Commission. Your comments should focus on the potential 

environmental effects, reasonable alternatives (including alternative 

facility sites and pipeline routes), and measures to avoid or lessen 

environmental impacts. The more specific your comments, the more useful 

they will be. To ensure that your comments are timely and properly 

recorded, please follow these instructions:

     Send an original and two copies of your letter to: Magalie 

R. Salas, Secretary, Federal Energy Regulatory Commission, 888 First 

St., NE., Room 1A, Washington, DC 20426 .

     Label one copy of your comments for the attention of DG2E/

G3.

     Reference Docket Nos. PF06-25-000 and PF06-26-000 on the 

original and both copies.

     Mail your comments so that they will be received in 

Washington, DC on or before July 24, 2006. We will provide the Coast 

Guard with copies of all comments received by the FERC during the 

scoping period.

    The Commission strongly encourages electronic filing of any 

comments in response to this NOI. For information on electronically 

filing comments, please see the instructions on the Commission's Web 

site at http://www.ferc.gov under the ``e-Filing'' link and the link to 



the User's Guide as well as information in 18 CFR 385.2001(a)(1)(iii). 

Before you can file comments you will need to create a free account, 

which can be accomplished on-line.

    The public scoping meetings (dates, times, and locations listed 

above) are designed to provide another opportunity to offer comments on 

the proposed project. Interested groups and individuals are encouraged 

to attend the meetings and to present comments on the environmental 

issues that they believe should be addressed in the EIS. A transcript 

of each meeting will be generated so that your comments will be 

accurately recorded.

    Once Jordan Cove and PCGP formally file their applications with the 

Commission, you may want to become an ``intervenor,'' which is an 

official party to the proceeding. Intervenors play a more formal role 

in the process and are able to file briefs, appear at hearings, and be 

heard by the courts if they choose to appeal the Commission's final 

ruling. An intervenor formally participates in a Commission proceeding 

by filing a request to intervene. Instructions for becoming an 

intervenor are included in the User's Guide under the ``e-filing'' link 

on the Commission's Web site. Please note that you may not request 

intervenor status at this time. You must wait until a formal 

application is filed with the Commission.



[[Page 37567]]



Environmental Mailing List



    If you wish to remain on the environmental mailing list, please 

return the attached Mailing List Retention Form (Appendix 2 of this 

NOI). If you do not return this form, we will remove your name from our 

mailing list.

    To reduce printing and mailing costs, the draft and final EIS will 

be issued in both compact disk (CD-ROM) and hard copy formats. The FERC 

strongly encourages the use of CD-ROM format in its publication of 

large documents. Thus, all recipients will automatically receive the 

EIS on CD-ROM. If you wish to receive a paper copy of the draft EIS 

instead of a CD-ROM, you must indicate that choice on the return 

mailer.



Additional Information



    Additional information about the project is available from the 

Commission's Office of External Affairs, at 1-866-208-FERC (3372) or on 

the FERC Internet website (http://www.ferc.gov) using the ``eLibrary 



link.'' Click on the eLibrary link, select ``General Search'' and enter 

the project docket number excluding the last three digits (i.e., PF06-

25 or PF06-26) in the ``Docket Number'' field. Be sure you have 

selected an appropriate date range. For assistance with eLibrary, the 

eLibrary helpline can be reached at 1-866-208-3676, TTY (202) 502-8659, 

or by e-mail at FercOnlineSupport@ferc.gov. The eLibrary link on the 

FERC Internet Web site also provides access to the texts of formal 

documents issued by the Commission, such as orders, notices, and rule 

makings.

    In addition, the FERC now offers a free service called 

eSubscription that allows you to keep track of all formal issuances and 

submittals in specific dockets. This can reduce the amount of time you 

spend researching proceedings by automatically providing you with 

notification of these filings, document summaries, and direct links to 

the documents. To register for this service, go to http://www.ferc.gov/esubscribenow.htm

.



    Public meetings or site visits will be posted on the Commission's 

calendar located at http://www.ferc.gov/EventCalendar/EventsList.aspx 



along with other related information.

    Finally, Jordan Cove and PCGP have established their own Internet 

websites for this project. The Web sites includes a project overview, 

status, answers to frequently asked questions, and links to related 

documents. The Jordan Cove Web site is at http://www.jordancoveenergy.com The PCGP Web site is at http://.



http://www.pacificconnectorgp.com. Additional information can be obtained 



directly from Jordan Cove by calling Bob Braddock at 541-266-7510 (e-

mail: bobbraddock@attglobal.net) or from PCGP by calling Jan Camp at 

360-666-2106 (e-mail: pacificconnector@williams.com).



Magalie R. Salas,

Secretary.

[FR Doc. E6-10304 Filed 6-29-06; 8:45 am]



BILLING CODE 6717-01-P